Phase 1 of the five year streetscape program begins next week with the underground work.
Construction work on the utility upgrades associated with the first phase of the five year Central Business District Streetscape program is scheduled to begin during the week of October 30. This work will consist of the installation of new water mains, hydrants and water services with work starting on South Grove Avenue, at Chicago Street and proceeding south. The overall first phase project will include utility work on Grove Avenue, between Highland Avenue and Prairie Street, Fulton Street between Villa Street and Spring Street, and Spring Street between Chicago Street and Fulton Street/Grove Street.
The nature of the utility construction in the downtown area will create many challenges. The construction will be planned and executed in order to maintain reasonable access during construction, and minimize disruption to the extent possible. During the project, an ongoing public involvement and outreach effort will be maintained to keep stakeholders and the general public informed including newsletters, updates, and project status reports via mailings/handouts and on the City’s website.
The construction work on Chicago Street is part of a multi-year sewer separation project for all of Elgin. It was moved up in the schedule so it wouldn't interfere with the streetscape work.
For further information, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.
UPDATE: The project start date has been changed to November 6th so it doesn't conflict with the ongoing sewer separation work.