Downtown Elgin Streetscape Phase 2

We are in year two of a six year City of Elgin program to replace the water mains, separate sanitary and storm sewers and install new sidewalks, curbs and street resurfacing throughout downtown Elgin.

Phase 2 consists of the following areas:
Chicago St. from Riverside Drive to Villa St.
Grove from Highland to just south of Chicago St.
Spring St. from Chicago to Highland
and Douglas from Chicago St. to the alley north of Chicago.
Construction will be completed in 7 stages starting June 23rd, each lasting approximately 3 weeks, with final completion scheduled for Thanksgiving of 2008.

Stages
1. South side of Chicago Street - Riverside Drive to S. Grove Ave.; west side of S. Grove around Fountain Square Plaza.
2. East side of S. Grove Avenue (from alleyway); south side of Chicago Street – S. Grove to Spring Street; west side of Spring Street.
3. East side of Spring Street; south side of Chicago Street - Spring Street to Villa Court.
4. North side of Chicago Street – Riverside Drive to north Grove; west side of north Grove Avenue.
5. East side of north Grove Avenue; north side of Chicago – south Grove to Douglas Avenue; west side of Douglas Avenue.
6. East side of Douglas; north side of Chicago – Douglas Avenue to Spring Street; west side of Spring Street.
7. East side of Spring Street; north side of Chicago – Spring Street to Villa Court (Center Street).

This is the result from Phase 1
Please visit downtownelgin.info for project details. Click here to view the blog posts related to the project.