Elgin – Phase III of the Central Business District’s $40 million Street Resurfacing and Streetscape Project is again underway as the City of Elgin continues to work toward the revitalization of its downtown area.

Water main service construction on Douglas Ave. between Highland Ave. and Dexter Court continues the week of April 6, 2009. Two-way traffic will be maintained and motorists will be able to maneuver through the work zone with flagger assistance.

On street parking will be limited during construction.  Patrons wishing to access businesses within this construction zone are encouraged to use the City Hall parking lot on the northwest corner of Douglas Ave. and Highland Ave.  Pedestrian access through and around the construction zone will be maintained.

Water main installation on Spring St. at Division and Center Streets and at Symphony Way between Center St. and Dundee Ave also continues this week.  Center St. at Symphony Way will be closed briefly during the installation of the water main.  Access to businesses on Center St. north of Symphony Way can be attained from Kimball Street.  Access to businesses on Center Street south of Symphony Way will be available from Symphony Way and will be directed by flaggers.  Parking is restricted in the construction zones, but is available along area streets. Motorists are asked to use caution when traveling. 

Lane closures will occur during normal working hours, approximately 7 a.m. through 4:30 p.m.  All lanes will be open during the overnight hours.

PHASE II STREETSCAPE CONSTRUCTION

Installation of the brick paver crosswalks on Chicago St. between Riverside Dr. and Center St./Villa Court and the adjacent side streets, Grove and Douglas Avenues and Spring St. is scheduled to begin April 27.  Completion of the crosswalks is expected to take approximately two weeks once construction begins.  Detailed information on construction schedules and lanes closures will be available prior to the start of the work.

Weekly progress meetings for the water main project are held on Thursdays at 8:30 a.m. at the construction office located at 201 E. Chicago Street.  Business and property owners are invited to attend the first 15 minutes of the meeting to address questions or concerns regarding the construction. 

Specific construction questions can be directed to Shelley Costello with TranSystems at 847-871-3185.

For general information, contact Joe Evers at 847-931-5955 or visit the City’s website at www.cityofelgin.org or Gettin’ Around in Downtown

Monday, March 30, 2009

Downtown Street Work - March 30th

Douglas between Highland & Dexter Ct, Division/Symphony Way between Douglas & Center
 
Elgin - Phase III of the Central Business District’s $40 million Street Resurfacing and Streetscape Project is again underway as the City of Elgin continues to work toward the revitalization of its downtown area.
Water main service construction on Douglas Ave. between Highland Ave. and Dexter Court continues the week of March 30, 2009. Two-way traffic will be maintained and motorists will be able to move through the work zone with flagger assistance.
On street parking will be limited during construction. Patrons wishing to access businesses within this construction zone are encouraged to use the City Hall parking lot on the northwest corner of Douglas Ave. and Highland Ave. Pedestrian access through and around the construction zone will be maintained.
Water main installation on Division St. between Douglas Ave. and Center St. and on Symphony Way also between Douglas Ave. and Center St. continues this week. Two-way traffic on Division St. and Symphony Way will be maintained, but flaggers may direct traffic around the construction. Parking is restricted in the construction zones, but is available along area streets. Motorists are asked to use caution when traveling.
These lane closures will occur during normal working hours, approximately 7 a.m. through 4:30 p.m. All lanes will be open during the overnight hours.

Phase II Streetscape Construction
Installation of the brick paver crosswalks on Chicago St. between Riverside Dr. and Center St./Villa Court and the adjacent side streets, Grove and Douglas Avenues and Spring St. is scheduled to begin mid-April. Completion of the crosswalks is expected to take approximately two weeks once construction begins. Detailed information on construction schedules and lanes closures will be available prior to the start of the work.

Weekly progress meetings for the water main project are expected to be held on Wednesdays at 8:30 a.m. at the construction office located at 201 E. Chicago Street. Business and property owners are invited to attend the first 15 minutes of the meeting to address questions or concerns regarding the construction. It’s anticipated that the meetings will begin within the next few weeks.

Specific construction questions can be directed to Shelley Costello with TranSystems at 847-871-3185.
For general information, contact Joe Evers at 847-931-5955 or visit the City’s website at www.cityofelgin.org or Gettin’ Around in Downtown

Monday, March 23, 2009

Downtown Street Work - March 23rd

Construction continues week of 3/23. West (southbound) side of Douglas temporary lane closures.

Elgin - Phase III of the Central Business District’s $40 million Street Resurfacing and Streetscape Project is again underway as the City of Elgin continues to work toward the revitalization of its downtown area.

Water main service construction on Douglas Ave. between Chicago St. and Highland Ave. continues the week of March 23, 2009. With the west (southbound) side of Douglas Ave. under construction, temporary lane closures will be required to accomplish the work. Southbound traffic on Douglas Ave. will be detoured west on Highland Ave. to Grove Ave. Motorists will then turn south on Grove Ave. to Chicago St., head east on Chicago St. back to Douglas Ave. where traffic can continue south on Grove Ave. Northbound traffic will be allowed on Douglas Ave. through the work zone.

On street parking will be limited during construction. Patrons wishing to access businesses within this construction zone are encouraged to use the City Hall parking lot on the northwest corner of Douglas Ave. and Highland Ave. Pedestrian access through and around the construction zone will be maintained.

Water main installation on Division St. between Douglas Ave. and Center St. and on Symphony Way also between Douglas Ave. and Center St. continues this week. Two-way traffic on Division St. and Symphony Way will be maintained, but flaggers may direct traffic around the construction. Parking is restricted in the construction zones, but is available along area streets. Motorists are asked to use caution when traveling.

These lane closures will occur during normal working hours, approximately 7 a.m. through 4:30 p.m. All lanes will be open during the overnight hours.
Phase II Streetscape Construction
Installation of the brick paver crosswalks on Chicago St. between Riverside Dr. and Center St./Villa Court and the adjacent side streets, Grove and Douglas Avenues and Spring St. is scheduled to begin mid-April. Completion of the crosswalks is expected to take approximately two weeks once construction begins. Detailed information on construction schedules and lanes closures will be available prior to the start of the work.

Weekly progress meetings for the water main project are expected to be held on Wednesdays at 8:30 a.m. at the construction office located at 201 E. Chicago Street. Business and property owners are invited to attend the first 15 minutes of the meeting to address questions or concerns regarding the construction. It’s anticipated that the meetings will begin within the next few weeks.

Specific construction questions can be directed to Shelley Costello with TranSystems at 847-871-3185.

For general information, contact Joe Evers at 847-931-5955 or visit the City’s website at www.cityofelgin.org and click the Gettin’ Around in Downtown link.

Sunday, March 15, 2009

They're Back!

Water Main Construction Resumes - Temporary Lane Closures on Douglas Avenue
Elgin - CENTRAL BUSINESS DISTRICT PHASE 3 WATER MAIN CONSTRUCTION RESUMES


Weather permitting, construction work on the water main crossings on Douglas Avenue will resume on Monday, March 16th at 7 a.m. and will require temporary lane closures to accomplish the work. As work begins on the west (southbound) side of Douglas, the southbound traffic will be detoured west on Highland Avenue to Grove Avenue, south on Grove Avenue to Chicago Street and east on Chicago Street back to Douglas where traffic can continue south on Grove Avenue. Northbound traffic will be allowed on Douglas Avenue through the work zone.
When the water main crossing moves to the east (northbound) side of Douglas Avenue, northbound Douglas Avenue will be detoured at Chicago Street east to Spring Street, north on Spring Street to Highland Avenue, west on Highland Avenue back to Douglas where northbound traffic can continue north on Douglas Avenue. During this stage of the work, southbound traffic will be allowed on Douglas Avenue through the work zone.
On street parking will be limited during construction. Patrons wishing to access businesses within the construction zone are encouraged to use the City Hall parking lot on the northwest corner of Douglas Avenue and Highland Avenue. Pedestrian access through and around the construction zone will be maintained.
These lane closures will occur during normal working hours, approximately 7 a.m. through 4:30 p.m. All lanes will be open during the overnight hours.
On Division Street, pavement sawcutting will begin on Monday March 16th at 7 a.m. weather permitting. Traffic will remain open at all times and directed by a flagger.
Weekly progress meetings for the water main project are held on Wednesdays at 8:30 a.m. at the construction office located at 201 E. Chicago Street. Business and property owners are invited to attend the first 15 minutes of the meeting if they have any questions or concerns regarding the construction.
Specific questions regarding the construction can be directed to Shelley Costello with TranSystems at 847-871-3185.
For general information on the project, please contact Joe Evers at 847-931-5964 or visit the City’s website at www.cityofelgin.org and click the Gettin’ Around in Downtown link.

Monday, June 23, 2008

Downtown Elgin Streetscape Phase 2

We are in year two of a six year City of Elgin program to replace the water mains, separate sanitary and storm sewers and install new sidewalks, curbs and street resurfacing throughout downtown Elgin.

Phase 2 consists of the following areas:
Chicago St. from Riverside Drive to Villa St.
Grove from Highland to just south of Chicago St.
Spring St. from Chicago to Highland
and Douglas from Chicago St. to the alley north of Chicago.
Construction will be completed in 7 stages starting June 23rd, each lasting approximately 3 weeks, with final completion scheduled for Thanksgiving of 2008.

Stages
1. South side of Chicago Street - Riverside Drive to S. Grove Ave.; west side of S. Grove around Fountain Square Plaza.
2. East side of S. Grove Avenue (from alleyway); south side of Chicago Street – S. Grove to Spring Street; west side of Spring Street.
3. East side of Spring Street; south side of Chicago Street - Spring Street to Villa Court.
4. North side of Chicago Street – Riverside Drive to north Grove; west side of north Grove Avenue.
5. East side of north Grove Avenue; north side of Chicago – south Grove to Douglas Avenue; west side of Douglas Avenue.
6. East side of Douglas; north side of Chicago – Douglas Avenue to Spring Street; west side of Spring Street.
7. East side of Spring Street; north side of Chicago – Spring Street to Villa Court (Center Street).

This is the result from Phase 1
Please visit downtownelgin.info for project details. Click here to view the blog posts related to the project.

Saturday, May 17, 2008

Bike Racks and More...


New bike racks have been installed on DuPage Court. Two racks in the style of old fashioned "high wheel" bikes bookend the court. Other bike rack locations here.
Six loop racks dot the court.
A new restaurant called Mad Maggies is coming soon at the Grove Ave side of the court and Al's Cafe has a new projecting sign over on the Spring St side.
One more thing...

The new trees are in on Grove Ave, a welcome sight. So ride your bike down to DuPage Court and have a malt, take in the sights and sometime in the future you can have a pizza too.

Saturday, December 01, 2007

Walking in a Winter Wonderland

And Bob in his hardhat and Joe on his Cat have just settled down for a long winter’s nap.

Construction has come to a close on Phase I of the Downtown Elgin Streetscape Plan, just in time for a flurry of holiday activities.

Though a few barricades and sandbags remain, not a dump truck will be stirring, not even a drill until early next year.

Okay, enough with the forced ‘Twas the Night Before Christmas metaphors – they just don’t really work with construction terminology.

Anyway, it’s the most wonderful time of the year to come downtown and see what you’ve been missing. Starting today.

Ever seen a real live reindeer? Dasher, Dancer, Prancer and the whole gang is hanging out in the City Hall parking lot today. No, they’re not awaiting their court date, though they are a wily crew. They are part of the Downtown Neighborhood Association’s annual Window Wonderland event happening today all throughout downtown Elgin.

Santa’s here too making a special appearance to promote his new movie. That guy is always reinventing himself. He’s like the Travolta of the North Pole. The kiddies can have lunch with him at The Centre from 11 to 12:30 or 1 to 2:30 – just give a call to 847-931-6100 to pre-register. Santa will also be available for free pictures in the Professional Building at 164 Division Street from 12 to 5pm. How can Santa be in two places at once, you ask? As my nephew would say, “Duh, he’s Santa.” Duh.

There’s also a live nativity scene in the parking lot next to the Galleria on North Grove with Larkin Avenue Baptist Church presenting a narration of the Gospel of Luke. Carolers will accompany the “bahs” and “moos”.

Now the main event, as the name implies, are the decorated storefront windows sprinkled throughout downtown. More than 25 businesses and volunteer groups decorated windows in the theme of “Holidays of the Past, Present and Future.” You’ll get a passport to help you make your way around downtown to find the windows. You can travel by foot or by trolley to survey the handiwork and then vote for your favorite. Many of the businesses are offering free hot chocolate and other goodies and lots of fun activities so be sure to stop in and get your passport stamped.

The day closes with fun in Festival Park as the city presents its annual tree lighting ceremony beginning at 5pm, complete with free sleigh rides and readings of the Polar Express.

So bring the family down for some holiday fun. You’ll be surprised to see what a few watts of electricity and a little holiday cheer can do. No doubt you’ll have visions of downtown Elgin dancing in your head.

Monday, June 25, 2007

Central Business District Streetscape Project Kick-off Meeting


Wednesday, June 27, 2007
Elgin Area Chamber Office
31 South Grove Avenue
12 Noon – 1 PM
Lunch will be provided

The City of Elgin is hosting a lunch meeting Wednesday, June 27 beginning at 12 noon to provide downtown business and property owners and other key stakeholders an opportunity to learn about the CBD Streetscape Project scheduled to begin within the next few weeks. The meeting will address the anticipated construction schedule and its impact on downtown vehicle and pedestrian traffic. Lunch will be provided.

Phase I of the construction project includes the installation of all new streets and curbs, sidewalks with brick pavers, brick crosswalks, planters, trees and street lighting. Impacted streets during Phase I are: south Grove Avenue between Chicago Street and Prairie Street; Spring Street between Chicago Street and Fulton Street; DuPage Street between Spring Street and Villa Street; and Fulton Street between Spring Street and Villa Street.

This is part of a 5-year, $22 million downtown business district improvement plan.

Friday, April 27, 2007

City Launches "Gettin' Around in Downtown" Communication Campaign

The city of Elgin launched a communications campaign called, "Gettin' Around in Downtown", to inform the public about the five year program for replacing water mains, streets and sidewalks.

Elements of the campaign include...
  • A new web site, www.downtownelgin.info
  • A town hall meeting in May (Date to be determined)
  • A hotline at 847.931.6767

Read the Daily Herald article from April 27th here.
Stayed tuned for more information.

Saturday, April 21, 2007

Downtown Elgin Water Main Construction Updates - April 23

Water Main Installation Construction Continues Through the Week of April 23

ELGIN – Work continues on the Central Business District Street Resurfacing and Streetscape project with the installation of individual water services on Spring Street between Chicago and DuPage Streets the week of April 23.

Northbound traffic on Spring Street will be diverted east on DuPage Street to Villa Street. Southbound traffic on Spring Street will be able to proceed as usual. Two-way traffic will be maintained on Grove Street south between Chicago and Prairie Streets, however, motorists wishing to travel northbound on Spring Street may use Grove Street as an alternative.

Sidewalk, curb and gutter restoration on Grove Street south between Chicago and Fulton Streets will begin mid-week. While two-way traffic will be maintained, flaggers will be directing a single lane of traffic around the construction at times. Motorists are asked to pay special attention when traveling through this area or to avoid the construction zone by using alternate routes.

Specific questions regarding the construction can be directed to Shelley Costello with TranSystems at 847-871-3185. For general information on the project, please contact Steve Pertzborn, Elgin’s Senior Engineer, at 847-931-5955.

Friday, April 13, 2007

Spring Street Water Main Construction

Construction Continues on New Water Main

Work will begin on the installation of the new water main on Spring Street between Chicago Street and Dupage Street. On Monday, April 16th, traffic control will be set up to allow construction of the new water main. Northbound traffic on Spring Street between DuPage Street and Chicago Street will not be allowed during this phase. Northbound traffic will be diverted east on DuPage Street to Villa Street. During this period of construction, two-way traffic will be maintained on south Grove Street and motorist wishing to travel northbound may want to use Grove Ave as an alternative. Southbound traffic on Spring Street will be allowed.

Sidewalk and curb and gutter restoration on south Grove Ave between Chicago Street and Fulton may begin on Wednesday. While two way traffic will be maintained, there may be times when flaggers will be directing single lane of traffic around the construction operation. Motorists are asked to pay attention when traveling through this area and to avoid the construction zone whenever possible.

Specific questions regarding the construction can be directed to Shelley Costello with TranSystems at 847-871-3185 or at her office in the back of the Downtown Neighborhood Association office at 2 Douglas Ave.

For general information on the project, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.

Friday, April 06, 2007

Water Main Replacement Continues on South Grove

Water Main Installation Construction for the Week of April 9th.

Construction Continues on New Water Main
Installation of the individual services on south Grove Street between DuPage Court and Fulton / Spring Street will continue during the week of April 9 -13, 2007.

This work will require the closure of south Grove Street between Chicago and Spring Street to through traffic. Motorists wishing to travel south from Chicago Street should use Spring Street.
Access to local businesses from Chicago Street to DuPage Court will be allowed. Pedestrian access to local businesses south of DuPage Court will be allowed. People wishing to access these businesses are encouraged to use the Fulton Street garage. This section should be finished on Tuesday. Underground work on south Grove between Fulton and Prairie will take place on Wednesday, Thursday and Friday nights, beginning at 7 p.m. each evening. This block will be closed to all traffic. Southbound traffic from Spring and Grove Streets will be detoured eastbound on Fulton, south on Villa and back westbound on Prairie where they can continue south on Grove Street. Northbound traffic will be detoured eastbound on Prairie, southbound on Villa and back westbound on Fulton where they can continue northbound on either Grove or Spring Street.

Specific questions regarding the construction can be directed to Shelley Costello with TranSystems at 847-871-3185 or at her office in the back of the Downtown Neighborhood Association office at 2 Douglas Ave.

For further information, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.

Check downtownelgin.org for construction updates.

Friday, March 23, 2007

South Grove Street Closed March 26-30 for Water Main Work

South Grove Street between DuPage Court and Fulton and Spring Streets will be closed next week, March 26-30, as crews continue water main installation through the Central Business District.

Detour signs will direct south bound motorists to Spring Street. Pedestrian and vehicle access to local businesses from Chicago Street to DuPage Court will be allowed. Parking will be available in downtown's Fulton Street garage.
Downtown Elgin's water main installation work continues as part of the Central Business District $22 million street resurfacing and streetscape project. Construction crews have been working during the overnight hours to help reduce traffic congestion.

For more information, contact Steve Pertzborn, senior engineer, at 847-931-5955.

Thursday, March 08, 2007

UPDATE: South Grove Closed on Monday, March 12th

On Friday, March 9th Monday, March 12th, South Grove Street will be closed between E.Chicago Street and Spring Street to allow for installation of new storm sewer. It is anticipated that the road will be closed between 7am and 4pm. Local access to the Union Bank drive up will be allowed. For further information please contact Steve Pertzborn, Senior Engineer, at 847.931.5955.

Wednesday, March 07, 2007

Chicago Street Closed Today, March 7th

City to close part of Chicago Street today
Chicago Street will close between Grove Avenue and Spring Street between 7 a.m. and 3 p.m. today as city crews work to repair a water leak there.
Water service will be interrupted to area businesses and homes during the time the repair is being made.
"Water will be interrupted only as long as it takes to repair the leak," said Public Works Director John Loete. "However, if there is an inch or more of snow on the ground, the repair will be postponed."
Traffic will be detoured around the area, although crews will try to keep one lane open.
For more information, contact the Elgin Public Works Department at (847) 697-3160.

Thursday, December 07, 2006

Water Main Installation Night Work to Continue

Central Business District (CBD) Street Resurfacing and Streetscape Program

Weather permitting, construction of the new water main from Chicago Street south down South Grove Avenue will begin the week of December 11, 2006. This work will be done at night in order to minimize impact on downtown businesses and the motoring public. The far right lane on Chicago Street from the river to just east of South Grove Avenue will be closed as well as South Grove Avenue between Chicago Street and Prairie Street. The lane closures will begin at 9 p.m. each evening and will be reopened before 5 a.m. the following morning.

Parking along South Grove Avenue will not be allowed during the lane closures. All vehicles should be removed prior to 9 p.m.

Traffic wishing to travel north from Prairie or Fulton Street can use Spring Street as an alternate.

For further information, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.

Wednesday, November 22, 2006

Water Main Installation Being Done At Night

Construction of the new water main on and across Chicago Street is being done the week of November 20th at night in order to minimize impact on downtown businesses and the motoring public. This work will include the installation of water main along the south side of Chicago Street from North Grove, where new water main has already been installed, to South Grove. At that intersection, the water main installation will turn south along South Grove. No further water main work on Chicago Street is anticipated in this phase of the project.

Lane closures on Chicago Street will begin at 7 p.m. but the street will remain open to traffic. All lanes on Chicago will be open before the morning rush hour. Utility construction in the downtown area has created many challenges. The night construction for the crossing of Chicago Street is being utilized in order to maintain full access to businesses during the day and to minimize disruption to traffic during peak times.

For further information, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.

Friday, November 03, 2006

New Date for Start of Central Business District (CBD) Street Resurfacing

Central Business District (CBD) Street Resurfacing and Streetscape Program

Start Date for Central Business District Streetscape Program Rescheduled

Construction work on the utility upgrades associated with the first phase of the five year Central Business District Streetscape program has been re-scheduled to begin during the week of November 6. This work will consist of the installation of new water mains, hydrants and water services. Construction will now begin on North Grove Avenue at Highland Avenue. Work will proceed south to Chicago Street, east on Chicago Street to South Grove Avenue and then proceed south on South Grove to Prairie Street. The overall first phase of this project includes utility work on Grove Avenue, between Highland Avenue and Prairie Street, Fulton Street between Villa Street and Spring Street, and Spring Street between Chicago Street and Fulton Street/Grove Street.

The new start date of the construction and the change in the starting location was done to avoid conflict with the sewer separation work which is scheduled to be completed soon.

The nature of the utility construction in the downtown area will create many challenges. The construction will be planned and executed in order to maintain reasonable access during construction, and minimize disruption to the extent possible. During the project, an ongoing public involvement and outreach effort will be maintained to keep stakeholders and the general public informed including newsletters, updates, and project status reports via mailings/handouts and on the City’s website.

For further information, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.

Friday, October 27, 2006

Central Business District Streetscape Program Construction to Begin

Phase 1 of the five year streetscape program begins next week with the underground work.

Construction work on the utility upgrades associated with the first phase of the five year Central Business District Streetscape program is scheduled to begin during the week of October 30. This work will consist of the installation of new water mains, hydrants and water services with work starting on South Grove Avenue, at Chicago Street and proceeding south. The overall first phase project will include utility work on Grove Avenue, between Highland Avenue and Prairie Street, Fulton Street between Villa Street and Spring Street, and Spring Street between Chicago Street and Fulton Street/Grove Street.

The nature of the utility construction in the downtown area will create many challenges. The construction will be planned and executed in order to maintain reasonable access during construction, and minimize disruption to the extent possible. During the project, an ongoing public involvement and outreach effort will be maintained to keep stakeholders and the general public informed including newsletters, updates, and project status reports via mailings/handouts and on the City’s website.

The construction work on Chicago Street is part of a multi-year sewer separation project for all of Elgin. It was moved up in the schedule so it wouldn't interfere with the streetscape work.

For further information, please contact Steve Pertzborn, Senior Engineer, at 847-931-5955.

UPDATE: The project start date has been changed to November 6th so it doesn't conflict with the ongoing sewer separation work.

Wednesday, October 25, 2006

Five Year Streetscape Plan


The City of Elgin has engaged the services of TranSystems Corporation and DLK Civic Design to provide design services for water main and water service replacement, streetscape amenities construction and street resurfacing. The CBD Streetscape Improvement Project is in the City’s current five-year master plan with $15.5 million budgeted for utility and streetscape work.

Three public meetings have been held to collect input on sidewalk materials, trees and plantings and pedestrian access. The following links are the materials presented at the October 17th meeting:

Concepts
Elements

The Streetscape Master Plan is in the works and will be presented at the fourth public meeting.

This is the schedule:
2006 Underground, 2007 Surface: Sidewalk, curb and gutter and street reconstruction/resurfacing on sections of Grove, Spring and Fulton.

2007 Underground, 2008 Surface: Chicago Street from State to Center, Spring Street from Chicago to Highland, and DuPage Street from Spring to Center.

2008 Underground, 2009 Surface: Douglas Street from Chicago to Symphony, Symphony Way from Douglas to Dundee, and Division Street from Douglas to Center.

2009 Underground, 2010 Surface: Highland Avenue from State to Center, Grove Street from Highland to City Hall, and Center Street from Dexter to Kimball.

2010 Underground, 2011 Surface: Spring Street from Highland to Kimball and Dexter Avenue from City Hall to Center.